Zeta Theta Renovation Action Plan Summer `09 to Summer `10 UPDATED 6/16/2010

Zeta Theta Renovation Action Plan

7/16/2009 and updated 6/16/2010 (completion date in parentheses)


Brothers,
      The following is schedule of projects that will be completed in the near future. To date we have completed all rooms in the main house with the exception of minor detail work.


Summer 2009

OK
Prime and Paint (7/2009)
Carpet (7/2008)
Build Permanent Beds (7/2009)
Install outlets, switches, vents....etc (7/2008)

Ladies John
Prime and Paint (6/2009)
Tile Floor (6/2009)
Install Toilet, Shower Door and Trim (6/2009)

General
Trim Chapter Room
Trim Library
Trim Penthouse (3/2010)
Get Addition siding completed by contractors (10/2009)

TMA
Gut (7/2009)
Wire outlets and cans lights (8/2009)
Insulate (8/2009)
Plywood walls only (8/2009)
Drywall walls and ceiling (8/2009)
Mud (9/2009)
Prime and Paint (9/2009)
Carpet (10/2009)
Build Beds (9/2009)
Install outlets, switches, and vents covers (9/2009)


Fall 2009

Upper Addition Hall
Gut (7/2009)
Wire outlets and can lights (9/2009)
Insulate (10/2009)
Plywood walls only (10/2009)
Drywall walls and ceiling (11/2009)
Mud (1/2010)
Prime and Paint (2/2010)
Carpet (3/2010)

TEA
Gut (7/2009)
Wire outlets and cans lights (8/2009)
Insulate (9/2009)
Plywood walls only (9/2009)
Drywall walls and ceiling (10/2009)
Mud (1/2010)
Prime and Paint (2/2010)
Carpet (3/2010)
Build Beds (2/2010)

Spring 2010

TOS
Gut (7/2009)
Wire outlets and cans lights (10/2009)
Insulate (10/2009)
Plywood walls only (1/2010)
Drywall walls and ceiling (ceiling 10/2009)
Mud (1/2010)
Prime and Paint (2/2010)
Carpet (3/2010)
Build Beds (2/2010)

BRA
Gut (2/2010)
Wire outlets and cans lights (4/2010)
Insulate (4/2010)
Plywood walls only (4/2010)
Drywall walls and ceiling (4/2010)
Mud (5/2010)
Prime and Paint
Carpet
Build Beds

Summer 2010

BMA
Gut (4/2010)
Wire outlets and cans lights (4/2010)
Insulate (4/2010)
Plywood walls only (4/2010)
Drywall walls and ceiling (4/2010)
Install Slding Glass door for deck access
Mud
Prime and Paint
Carpet
Build Beds

3 Way (Old Crib Room)
Gut (6/2010)
Wire outlets and cans lights (6/2010)
Insulate (6/2010)
Plywood walls only
Drywall walls and ceiling
Mud
Prime and Paint


Carpet or Refinish Upper Main House

Tile Lower Foyer Floor

*This is a tentative schedule, but from previous term's progress and our experience, this seems feasible.

Please direct all questions, comments, and concerns to me and I will address them ASAP.


In Hoc,
Chris Channell
House Corporation Vice President
419-351-8873
Channell2002@hotmail.com

<< BACK TO PROJECTS PAGE

Zeta Theta

Zeta Theta Chapter House Restoration Committee  |  Email Us
Privacy Policy  |  Website Designed and Hosted by LogicalSolutions.net