Brothers, The following is schedule of projects that will be completed in the near future. To date we have completed all rooms in the main house with the exception of minor detail work.
Summer 2009
OK Prime and Paint (7/2009) Carpet (7/2008) Build Permanent Beds (7/2009) Install outlets, switches, vents....etc (7/2008)
Ladies John Prime and Paint (6/2009) Tile Floor (6/2009) Install Toilet, Shower Door and Trim (6/2009)
General Trim Chapter Room Trim Library Trim Penthouse (3/2010) Get Addition siding completed by contractors (10/2009)
TMA Gut (7/2009) Wire outlets and cans lights (8/2009) Insulate (8/2009) Plywood walls only (8/2009) Drywall walls and ceiling (8/2009) Mud (9/2009) Prime and Paint (9/2009) Carpet (10/2009) Build Beds (9/2009) Install outlets, switches, and vents covers (9/2009)
Fall 2009
Upper Addition Hall Gut (7/2009) Wire outlets and can lights (9/2009) Insulate (10/2009) Plywood walls only (10/2009) Drywall walls and ceiling (11/2009) Mud (1/2010) Prime and Paint (2/2010) Carpet (3/2010)
TEA Gut (7/2009) Wire outlets and cans lights (8/2009) Insulate (9/2009) Plywood walls only (9/2009) Drywall walls and ceiling (10/2009) Mud (1/2010) Prime and Paint (2/2010) Carpet (3/2010) Build Beds (2/2010)
Spring 2010
TOS Gut (7/2009) Wire outlets and cans lights (10/2009) Insulate (10/2009) Plywood walls only (1/2010) Drywall walls and ceiling (ceiling 10/2009) Mud (1/2010) Prime and Paint (2/2010) Carpet (3/2010) Build Beds (2/2010)
BRA Gut (2/2010) Wire outlets and cans lights (4/2010) Insulate (4/2010) Plywood walls only (4/2010) Drywall walls and ceiling (4/2010) Mud (5/2010) Prime and Paint Carpet Build Beds
Summer 2010
BMA Gut (4/2010) Wire outlets and cans lights (4/2010) Insulate (4/2010) Plywood walls only (4/2010) Drywall walls and ceiling (4/2010) Install Slding Glass door for deck access Mud Prime and Paint Carpet Build Beds
3 Way (Old Crib Room) Gut (6/2010) Wire outlets and cans lights (6/2010) Insulate (6/2010) Plywood walls only Drywall walls and ceiling Mud Prime and Paint
Carpet or Refinish Upper Main House
Tile Lower Foyer Floor
*This is a tentative schedule, but from previous term's progress and our experience, this seems feasible.
Please direct all questions, comments, and concerns to me and I will address them ASAP.
In Hoc, Chris Channell House Corporation Vice President 419-351-8873 Channell2002@hotmail.com